Dear Neighbors,

As part of a project to improve safety along Marlboro’s roads, the Highway Department will be replacing and upgrading GUARD RAILS on Higley Hill, Augur Hole (completed), North Pond, MacArthur, and South Roads.

This work will proceed as follows:
Higley Hill Road – May 7th.
Auger Hole, North Pond & MacArthur Roads – May 8th & 11th.
South Road – May 12th.

During this work, the roads WILL NOT be closed to traffic, but there may be intermittent delays to insure the safety of the road workers…”Flaggers” will be present to direct traffic.

The Highway Department greatly appreciates your patience during this work.

Thank you, Your Marlboro Highway Department